NO.39 When scheduling the Update Project Performance Data process to run on a periodic basis, whichsummarization method would you select? (

 
 
 
 

NO.40 Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets basedon the construction-in-process cost of each asset.Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)

 
 
 
 
 

NO.41 Select two correct statements about project classifications on a template. (Choose two.)

 
 
 
 

NO.42 Which application generates external roles to grant both function and data security? (Choose the best answer
.)

 
 
 
 

NO.43 Your customer has separate organizationsto maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (Choose two.)

 
 
 
 
 

NO.44 You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contractLine 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X – Task 10, and Bill Plan B is allocated against Project Y – Task
30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)

 
 
 
 

NO.45 Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes/No. But on creation of a project, you are unable to associate these classcategories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)

 
 
 
 

NO.46 Which two privileges are assigned to the Project Plan Management duty in Security Reference Implementation? (Choose two.)

 
 
 
 

NO.47 As part of maintaining (importing new employees thatwere added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Whichthreeare parameters that are based on which the system identifies the new resources?

 
 
 
 
 

NO.48 Which application would you use to map application roles to external roles? (Choose the best answer.)

 
 
 
 

NO.49 Your administrator creates maintenance conditions on the Maintain Project Enterprise Labor Resources page.
An HCM person is included in a condition with a process ordervalue of 1 and, additionally, there are three other conditions, all with a process order value of 10. Identify two correct statements about the Maintain Project Enterprise Labor Resources process as it relates to process order values. (Choose two.)

 
 
 
 

NO.50 Your customer wants a projectstart date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this.(Choose the best answer.)

 
 
 
 

NO.51 Which two statements describe how the Resource Qualification Score is calculated?

 
 
 
 

NO.52 Your customer wants a team member who is assigned to a project to beable to create and submit a forecast, butnot to be able to approve the forecast. What is the default project rolethat you should assign to the person in the project to meet this requirement? (Choose the best answer.)

 
 
 
 

NO.53 Identifythethreecontract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three

 
 
 
 
 

NO.54 Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost andActual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

 
 
 
 

NO.55 Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)

 
 
 
 

NO.56 You have been asked to set up one active person, who is not a team member in the project, as a quality manager for each quality task created underprojects. However, when you try to assign the quality manager as Task Manager, you cannot find the person’s name in the list of values. What is the reason for this problem?
(Choose the best answer.)

 
 
 
 

NO.57 You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
AssociatedProject Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)

 
 
 
 

NO.58 You want tocreate a few project roles so as to restrict accessin the Project Financial Management work area to only the specific projects in which an employee is assigned as a team member. What are the two default project roles available to meet this requirement? (

 
 
 
 
 

NO.59 While creating a new project template, you notice that a default Asset Cost Allocation method is being automatically associated. Identify the source setup from which the default value is being inherited. (Choose the best answer.)

 
 
 
 

NO.60 Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China andadded a China business unit. A project accountant in your organization is authorized to access transactions for the US, UK, and China business units. The project accountant can see the transactions for the US and UK business units but not for the China business unit. Why is he not able to see the transactions for the China business unit? (Choose the best answer.)

 
 
 
 

NO.61 Yourcustomer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)

 
 
 
 
 

Tested Material Used To 1Z0-1057-21 Test Engine: https://www.pdf4test.com/1Z0-1057-21-dump-torrent.html

Related Links: oyhta.org letterboxd.com www.grepmed.com myportal.utt.edu.tt myportal.utt.edu.tt fortunetelleroracle.com

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below